| 2026-04-26 |
Mounir, Giorgio, Vishaka, Chao, Amir, Giada |
Restart after CBI, define whether PackyTrace remains a DPP idea or becomes a startup project, identify first workstreams. |
The team agreed to continue PackyTrace as a startup-oriented project starting from the Digital Product Passport opportunity. The first scope was still broad: traceability, sustainability, consumer information, brand value and possible reward mechanisms were all considered. Mounir and Giorgio took ownership of turning the idea into a manageable plan; product research and market work were split across the team. |
| 2026-05-03 |
Mounir, Giorgio, Vishaka, Chao, Giada |
Compare possible value propositions, define early user segments, plan the first validation activities. |
The meeting showed that the original brand-first framing was too broad. The team decided to interview consumers and domain contacts before adding more features. The initial MVP candidates were product scan, personalized product explanation, expiry tracking and a simple brand dashboard. |
| 2026-05-10 |
Mounir, Giorgio, Vishaka, Giada |
Review early feedback, prepare interview questions, align on target users and public narrative. |
The team narrowed the likely target toward young adults who care about diet, fitness, health or sustainability but do not want long product pages. Giada supported interview planning and feedback collection. The team also agreed that Startup Day could be used as an external milestone rather than a final product launch. |
| 2026-05-17 |
Mounir, Giorgio, Chao |
Translate product direction into backlog areas, separate startup work from software-platform work, prepare questions for mentors. |
The team separated the work into two connected flows: startup validation and platform delivery. Mounir started turning the software side into domain analysis, architecture, contracts and a thin end-to-end slice. Giorgio focused on business-model assumptions and stakeholder positioning. |
| 2026-05-24 |
Mounir, Giorgio, Vishaka, Amir |
Review scope risk, decide what must stay out of the MVP, prepare the first mentor check with Davide. |
The team recognized the risk of scope creep. Reward systems, a full AI assistant, community features and a polished B2B dashboard were moved outside the immediate MVP. Amir gave input on sustainability messaging, but the group decided not to make sustainability the only reason to scan. |
| 2026-05-31 |
Mounir, Giorgio, Vishaka, Chao |
Consolidate the MVP backlog, define the weekly execution rhythm, assign platform and pitch tasks. |
The team adopted Sunday meetings as the main weekly control point. The backlog was organized around scan, profile, personalized verdict, Fridge, trust/privacy and brand dashboard. ClickUp remained the shared work tracker; WhatsApp was used for fast coordination. |
| 2026-06-07 |
Mounir, Giorgio, Vishaka |
Review mentor feedback, apply the consumer-first pivot, update priorities for software and pitch. |
After mentor and interview feedback, the team made the consumer-first direction explicit: PackyTrace should first help the person holding the product, then use engagement to justify brand analytics. Gamification was not deleted forever, but it was removed from the MVP. |
| 2026-06-14 |
Mounir, Giorgio, Chao |
Check progress toward Startup Day, stabilize the demo strategy, review documentation and pitch material. |
The team agreed to keep a safe demo path while continuing the real platform work. Mounir focused on CI, documentation, deployment and the demonstrable software flow. Giorgio and Chao focused on communication and presentation material. |
| 2026-06-21 |
Mounir, Giorgio, Chao |
Final pre-event review, confirm deliverables, define feedback-capture plan. |
The team treated Startup Day as a phase acceptance milestone. The decision was to show the platform as a concrete MVP, collect feedback systematically and avoid claiming full validation before real user and brand evidence existed. Next-cycle priorities were defined as user tests, more interviews, brand validation, LOI/pilot attempts and funding. |
| 2026-06-22 |
Mounir, Giorgio, Vishaka, Chao |
Complete the Startup Day presentation, align logistics for the event, assign final preparation tasks. |
The team reviewed the pitch structure, refined the wording around PackyTrace's consumer-first value proposition and checked that the public narrative stayed consistent with the MVP scope. The meeting also covered practical organization for the event: who would handle the pitch, who would support demo and networking, what material had to be ready, and how feedback would be captured for the next project cycle. |